Estero Approved the Rail Trail Purchase. Here's the Clock That Starts Next.

The old Seminole Gulf Railway tracks still run through Estero, and an unused rail bridge still crosses the corridor. On Oct. 28, the Estero Village Council voted unanimously to let staff close on buying the village's stretch of that line, which will become the Bonita Estero Rail Trail. The purchase covers 66.7 acres for $19,792,209, and closing is set for on or before Jan. 14, 2027.

Village Manager Steve Sarkozy told Gulfshore Business that "this is the final step in the process to acquire the Bonita Estero Rail Trail," after more than three years of discussion and negotiation. He's right about the purchase. For anyone in Estero who wants to walk, run or ride this corridor, though, the vote mostly sets a clock running. The first stretch of that clock is when the shape of the trail gets decided, and that comes years before any pavement.

What the Oct. 28 Vote Actually Settled

Estero signed its purchase-and-sale agreement with the Trust for Public Land on March 5, 2026. The agreement included a due diligence period, a window to inspect the property and walk away if needed. Once that window closed, the village would be committed to the purchase. On Sept. 23, an amendment pushed the inspection deadline to Oct. 29 and moved closing to on or before Jan. 14, 2027.

That makes the Oct. 28 meeting, held the day before the deadline, the last point where the village could have backed out. Most of the meeting was spent on the soil. According to the Village of Estero's meeting summary, Richard Stephens of S&S Environmental Consultants reported 69 soil samples taken from 23 locations inside Estero. Guri Zeigerman of Apex Engineering peer-reviewed the findings and agreed with them.

Gulfshore Business reported the corridor-wide numbers. Across all 11.4 miles, 180 samples were taken at 60 locations. The study found elevated arsenic and polynuclear aromatic hydrocarbons at several spots in Estero, Bonita Springs and Collier County, which is what you'd expect from land used as an industrial rail corridor since the 1920s. Zeigerman told the outlet the concentrations are "very typical and things that are pretty easily managed through engineering controls."

That review was the last open item, so the purchase is now set to close. Estero's vote also completed the corridor-wide deal, because the village was the last of three buyers to sign off.

Three Buyers, One January Closing

The Trust for Public Land negotiated the $60 million Phase 1 agreement with Seminole Gulf Railway and split the cost among three governments.

Buyer Share of the $60 million How it was approved
Village of Estero $19,792,209 for 66.7 acres Council voted to proceed on Oct. 28, 2026
City of Bonita Springs $28.6 million Council approved the agreement March 25, 2026; voters approved a $35 million bond Aug. 18, 2026
Collier County $11.6 million Commissioners approved; funded through Conservation Collier

Bonita Springs has the largest share because about 5.8 of the 11.4 miles run through the city, WINK News reported. More than 68% of Bonita voters approved the bond. Mayor Mike Gibson called the result "as close to a mandate as we're going to get." Douglas Hattaway of the Trust for Public Land told WINK the referendum "fills the last piece of funding necessary for the acquisition of and some construction funding" for the trail.

The map matters for Estero readers. Phase 1 runs from Wiggins Pass Road in Collier County north to Estero Parkway, through downtown Bonita Springs and then Estero. Estero holds the northern end of the section being bought now. The full proposed corridor is 14.9 miles and continues north past Estero Parkway to Alico Road, just north of San Carlos Park. The plan is to connect it to the John Yarborough Trail to the north and the Paradise Coast Trail to the south, as part of a Florida Gulf Coast Trail running the length of Lee County.

The Clock That Starts in January

The rails don't come up when the deed changes hands. WINK laid out the steps that come after closing:

  1. Closing, on or before Jan. 14, 2027. This is the date set for the full $60 million purchase.
  2. Up to two years for the railroad to remove the tracks. Engineering and design work happens during this same window, so construction can start soon after the tracks are gone.
  3. At least a year of construction. "It's going to be two plus years, so they have two years to vacate the railway, and then we'll break ground, and it's probably going to be at least a year of construction," Gibson told WINK News.
  4. Possible phased openings. Gibson said parts of the trail could open in phases, but where construction starts depends on how engineering and design play out.

Apply that to a January 2027 closing. If the railroad uses its full two years, ground could break as late as early 2029, followed by at least a year of building. The sequence leaves a long stretch before any trail exists. That stretch is also when the design work happens, so the corridor's eventual shape gets settled during it.

The Design Window Is Where Estero's Trail Gets Decided

Nothing about the trail's final form has been settled. In the same WINK News report, Friends of BERT board member and architect Nathalie White described the project as a "corridor of activity." She said different sections could take on different identities depending on the communities they pass through. Her vision includes connections near the Estero River, recreation areas, Coconut Point, employment centers and downtown Bonita Springs, with room for public art along the way.

She also named the tradeoff that will shape each access point. "We have to be considerate of our neighbors and privacy," White told WINK. "We have to consider those two things: privacy and also access." She said community input will play a major role in where access points go and how each section connects to nearby neighborhoods and businesses.

In a June update, Friends of BERT said the design phase would begin once the corridor is publicly owned, with architects and engineering consultants working alongside a task force from all three jurisdictions. That's the period when Estero's trailheads, crossings and connections to the Estero River and Coconut Point areas will be drawn. It begins after the January closing and runs alongside track removal.

The group behind the effort is sizable. Friends of BERT was founded in 2022 and has grown to about 4,500 members, according to WINK. President and co-founder Deb Orton told the station, "We're leaving a legacy for the people that come after us."

Where BERT Turns Up on the Calendar This Month

You can't ride the corridor yet, but the project has public dates over the next few weeks:

  • Sunday, Nov. 15: The 4th Annual Ride for BERT. Riders leave from Trek Bike Shop of Estero at 8001 Plaza del Lago Drive, 8 to 11 a.m., on 15-mile and 30-mile routes on local roads. Proceeds go to the rail trail. Both distances are sold out, but the event page still has a donate option. Coconut Point Mall vendors are setting up food stations for riders after the ride.
  • Monday, Nov. 16: Friends of BERT monthly board meeting. 5 to 7 p.m. at The Brooks at Lighthouse Bay, 23740 Olde Lighthouse Road, Bonita Springs.
  • Wednesday, Nov. 18: Estero Village Council. 9:30 a.m. at Village Hall, 9401 Corkscrew Palms Circle. This replaces the Nov. 4 meeting, which was canceled.
  • Monday, Dec. 21: Friends of BERT monthly board meeting. Same time and location.

The next date to watch after these is Jan. 14, 2027, the deadline for closing. Once the corridor closes, the railroad's two-year track-removal window begins, and design work runs during that same period. That's when Estero's access points and connections near the Estero River and Coconut Point will be decided.

If you're curious how a trail like this could eventually change daily routines along the corridor, or how it could figure into a future move within Estero, Jill Nicholas follows these projects closely and is happy to talk them through. Request a Consultation, and we'll keep you posted as the closing and design milestones arrive.